PRARANCANGAN PABRIK PRECIPITATED CALCIUM CARBONATE (PCC) DARI BATU KAPUR DENGAN KAPASITAS 150.000 TON/TAHUN | ELECTRONIC THESES AND DISSERTATION

Electronic Theses and Dissertation

Universitas Syiah Kuala

    SKRIPSI

PRARANCANGAN PABRIK PRECIPITATED CALCIUM CARBONATE (PCC) DARI BATU KAPUR DENGAN KAPASITAS 150.000 TON/TAHUN


Pengarang

YUDHA MAULANA RAMADHAN - Personal Name;

Dosen Pembimbing

Muhammad Dani Supardan - 197207102000031002 - Dosen Pembimbing I
Umi Fathanah - 197404032000122001 - Dosen Pembimbing II
Fachrul Razi - 197610182006041003 - Penguji
Mukhlishien - 196208021992031003 - Penguji
Darmadi - 196603231993031003 - Penguji



Nomor Pokok Mahasiswa

1904103010068

Fakultas & Prodi

Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201

Subject
-
Kata Kunci
-
Penerbit

Banda Aceh : Fakultas Teknik Kimia., 2024

Bahasa

No Classification

-

Literature Searching Service

Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)

Prarancangan pabrik precipitated calcium carbonate (PCC) ini menggunakan batu kapur sebagai bahan baku. Kapasitas produksi pabrik PCC ini adalah 150.000 ton/tahun dengan hari kerja yaitu 330 hari/tahun, Bentuk perusahaan yang direncanakan adalah Perseroan Terbatas (PT) dengan menggunakan metode struktur garis dan staf. Kebutuhan tenaga kerja untuk menjalankan perusahaan ini berjumlah 131 orang. Pabrik PCC ini direncakan berlokasi di Desa Ciburuy, Kecamatan Padalarang, Kabupaten Bandung Barat, Provinsi Jawa Barat dengan luas tanah 30.700 m2. Sumber air pabrik PCC berasal dari Sungai Citarum, Provinsi Jawa Barat dan untuk memenuhi kebutuhan listrik diperoleh dari Perusahaan Listrik Negara (PLN) dan generator dengan daya 316.183 kW.
Hasil analisa ekonomi yang diperoleh sebagai berikut:
1. Fixed Capital Investment (FCI) = Rp 1.874.672.327.545
2. Working Capital Investment (WCI) = Rp 468.668.081.886
3. Total Capital Investment (TCI) = Rp 2.343.340.409.431
4. Total Production Cost (TPC) = Rp 1.003.234.664.304
5. Selling Price (SP) = Rp 2.127.619.855.622
6. Pay Out Time = 2,94 Tahun
7. Break Even Point = 24%
8. Internal Rate of return = 27%
9. Rate of Return = 35,99%

This preliminary of precipitated calcium carbonate (PCC) factory design use limestone as a raw material with the production capacity is 150,000 ton/year with work day about 330 days of a year. The planned form of company is a Limited Liability Company (Ltd). The factory plant is planned to be established in Ciburuy Village, Padalarang Subdistrict, West Bandung Regency, West Java Province. The workers needed to run this company amounted to 131 people. The area of land required to set up the factory is 30,700 m2. The water source of the PCC plant comes from the Citarum river, West Java Province and the electricity need is obtained from the State Electricity Company (PLN) and the Generator of 316,183 kW. The results of economic analysis are: 1. Fixed Capital Investment (FCI) = Rp 1,874,672,327,545 2. Working Capital Investment (WCI) = Rp 468,668,081,886 3. Total Capital Investment (TCI) = Rp 2,343,340,409,431 4. Total Production Cost (TPC) = Rp 1,003,234,664,304 5. Selling Price (SP) = Rp 2,127,619,855,622 6. Pay Out Time = 2.94 Tahun 7. Break Even Point = 24% 8. Internal Rate of return = 27% 9. Rate of Return = 35.99%