Electronic Theses and Dissertation
Universitas Syiah Kuala
THESES
FAKTOR-FAKTOR RISIKO DALAM PELAKSANAANRNPROYEK KONSTRUKSI JALAN RNDI PROVINSI ACEH
Pengarang
Rachmad Abdullah, St - Personal Name;
Dosen Pembimbing
Renni Angraini - 197109231997022001 - Dosen Pembimbing I
M. Isya - 196204111989031002 - Dosen Pembimbing II
Cut Zukhrina Oktaviani - 197310102008122001 - Penguji
Fachrurrazi - 197005062000121001 - Penguji
Nomor Pokok Mahasiswa
1804201010044
Fakultas & Prodi
Fakultas Teknik / Teknik Sipil (S2) / PDDIKTI : 22101
Subject
Kata Kunci
Penerbit
Banda Aceh : Program Studi Magister Teknik Sipil Unsyiah., 2022
Bahasa
No Classification
-
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
FAKTOR-FAKTOR RISIKO DALAM PELAKSANAAN PROYEK
KONSTRUKSI JALAN DI PROVINSI ACEH
Rachmad Abdullah
NIM 1804201010044
Program Studi Magister Teknik Sipil
Jurusan Teknik Sipil - Fakultas Teknik
Universitas Syiah Kuala
Abstrak
Pelaksanaan proyek konstruksi jalan di Provinsi Aceh sering dihadapkan dengan
berbagai risiko. Salah satu risiko yang sering terjadi adalah kurangnya penerapan
Keselamatan dan Kesehatan Kerja (K3) sehingga dapat mengakibatkan bahaya
kecelakaan bagi pengguna jalan. Penelitian ini bertujuan untuk menganalisis faktorfaktor
risiko dan faktor risiko yang dominan terjadi dalam pelaksanaan proyek
konstruksi jalan di Provinsi Aceh. Proyek konstruksi jalan di Provinsi Aceh yang
ditinjau bersumber dari Anggaran Pendapatan Belanja Aceh (APBA) tahun 20182021.
Penelitian
ini
menggunakan
metode
kuantitatif
melalui
kuesioner.
Responden
ditujukan
pada salah satu personil perusahaan kontraktor dengan kualifikasi
menengah yaitu project manager, site manager, quality engineer, dan quantity
engineer. Jumlah populasi perusahaan kontraktor sebanyak 331 perusahaan dan
sampel sebanyak 220 perusahaan. Teknik pengambilan sampel kontraktor sub
kualifikasi M1 dan M2 (simultan) digunakan proportionate stratified random
sampling, sedangkan sampel kontraktor sub kualifikasi M1 (parsial) digunakan
simple random sampling. Faktor-faktor risiko yang dievaluasi adalah faktor risiko
teknis, risiko keselamatan, risiko manusia, risiko ekonomi dan keuangan, risiko
politik/regulasi, risiko material, risiko manajerial, risiko desain dan dokumentasi,
risiko kriminal, dan risiko cuaca. Teknik analisis data digunakan statistik deskriptif,
uji validitas, uji reliabilitas, dan PCA. Hasil penelitian menunjukkan bahwa menurut
persepsi kontraktor sub kualifikasi M1 dan M2 terdapat 8 faktor risiko pada proyek
konstruksi jalan yaitu faktor risiko teknis, risiko tenaga kerja, risiko biaya, risiko
desain dan dokumentasi, risiko penjadwalan, risiko keselamatan, risiko inflasi, dan
risiko cuaca dengan varian (persentase terjadi) sebesar 73,501%. Menurut persepsi
kontraktor sub kualifikasi M1 terdapat 9 faktor risiko pada proyek konstruksi jalan
yaitu faktor risiko tenaga kerja, risiko biaya, risiko manajemen dan cuaca, risiko
teknis, risiko desain dan dokumentasi, risiko peralatan, risiko penjadwalan, risiko
keselamatan, dan risiko inflasi dengan varian sebesar 73,089%. Faktor risiko yang
dominan menurut persepsi kontraktor sub kualifikasi M1 dan M2 adalah faktor risiko
teknis dengan varian sebesar 22,777%. Faktor risiko yang dominan menurut persepsi
kontraktor sub kualifikasi M1 adalah faktor risiko tenaga kerja dengan varian sebesar
20,644%.
Kata Kunci: Risiko, proyek, konstruksi, jalan, PCA
RISK FACTORS IN THE IMPLEMENTATION OF ROAD CONSTRUCTION PROJECTS IN ACEH PROVINCE Rachmad Abdullah Student Number 1804201010044 Master Program of Civil Engineering Civil Engineering Department of Engineering Faculty University Syiah Kuala Abstract The implementation of road construction projects in Aceh province often faces various risks. One of the frequently occurring risks is the lack of application of occupational safety and health (K3), so that there is a risk of accidents for road users. This study aims to analyze the risk factors and the dominant risk factors encountered in the implementation of road construction projects in Aceh province. The verified road construction projects in Aceh Province are from the 2018-2021 Aceh Revenue and Expenditure Budget (APBA). This study uses quantitative methods through questionnaires. Respondents were directed to one of the contractor company's employees with intermediate qualifications, namely the project manager, site manager, quality engineer and quantity engineer. The total population of contractors is 331 companies and the sample includes 220 companies. Proportionally stratified random sampling was used as the sampling method for contractor M1 and M2 (concurrent) subqualifications, while simple random sampling was used for contractor M1 (partial) subqualification sampling. The risk factors assessed are technical risk, security risk, human risk, economic and financial risk, political/regulatory risk, material risk, managerial risk, design and documentation risk, criminal risk and weather risk. Data analysis techniques used descriptive statistics, validity testing, reliability testing, and PCA. The results show that according to the perception of the subqualification companies M1 and M2, there are 8 risk factors in road construction projects, namely technical risk factors, labor risk, cost risk, planning and documentation risk, schedule risk, safety risk, inflation risk and weather risk variance (percentage of occurrence) of 73.501%. According to the Contractor M1 sub-skill perception, there are 9 risk factors in road construction projects, namely labor risk, cost risk, management and weather risk, engineering risk, planning and documentation risk, equipment risk, schedule risk, safety risk and inflation risk with variances of 73.089%. The dominant risk factor after perception of the sub-qualification contractors M1 and M2 is the technical risk factor with a variance of 22.777%. The dominant risk factor according to the perception of the subqualification entrepreneur M1 is the work risk factor with a variance of 20.644%. Key Words: Risk, project, construction, road, PCA
ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH (Hamdani, 2016)
ANALISIS FAKTOR-FAKTOR RISIKO YANGRNMEMPENGARUHI BIAYA PELAKSANAAN PROYEKKONSTRUKSI GEDUNG BAGI PERUSAHAANRNKONTRAKTOR DI PROVINSI ACEH (IKHLAS KURNIAWAN, 2022)
ANALISIS RISIKO SUPPLY CHAIN PROYEK KONSTRUKSI JALAN DI ACEH (Chairina Miranda Sari, 2025)
ANALISIS RISIKO PADA PELAKSANAAN PROYEK KONSTRUKSI GEDUNG DI PROVINSI ACEH MENGGUNAKAN METODE FUZZY TOPSIS (Tri Yolanda Ariska, 2023)
PENGARUH KUALIFIKASI KONTRAKTOR TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI KOTA BANDA ACEH (ZUHRI, 2018)