PRARANCANGAN PABRIK BIODIESEL MENGGUNAKAN PROSES KATALITIK TRANSESTERIFIKASI DENGAN KAPASITAS 300.000 TON/TAHUN
Pengarang
Bella Tri Adinda - Personal Name;
Dosen Pembimbing
Sofyana - 197106261998022001 - Dosen Pembimbing I
Nomor Pokok Mahasiswa
2104103010005
Fakultas & Prodi
Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201
Penerbit
Banda Aceh : Fakultas Teknik., 2026
Bahasa
Indonesia
No Classification
660
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
Prarancangan pabrik biodiesel ini bertujuan untuk merancang fasilitas produksi
biodiesel berbahan baku crude palm oil (CPO), metanol, dan NaOH sebagai katalis. Proses
produksi menggunakan transesterifikasi, dengan tahap awal penghilangan FFA melalui
adsorpsi menggunakan bentonit dan pencucian menggunakan air hangat untuk
pemurniannya. Pabrik direncanakan beroperasi selama 330 hari per tahun secara kontinyu
selama 24 jam per hari, dengan kapasitas produksi sebesar 300.000 ton per tahun . Bentuk
perusahaan yang direncanakan merupakan perseroan terbatas (PT) menggunakan struktur
organisasi garis dan staff. Selain itu, kebutuhan tenaga kerja dalam menjalankan
perusahaan adalah 124 orang. Lokasi pabrik direncanakan di Desa Cot lagan CM,
Kecamatan Woyla , Kabupaten Aceh Barat, Provinsi Aceh, Indonesia, dengan luas 21.337
m
2
. Sumber air yang digunakan berasal dari Sungai Woyla dengan kebutuhan sebanyak
100.755,69 kg/hari. Dan untuk memenuhi kebutuhan listrik diperoleh dari perusahaan
listrik Negara (PLN) dan generator dengan daya 805,93 kW.
Hasil analisa ekonomi yang diperoleh adalah sebagai berikut:
a. Fixed Capital Investment (FCI)
: Rp 1.444.418.724.951
b. Working Capital Investment (WCI)
: Rp 254.897.422.050
c. Total Capital Investment (TCI)
: Rp 1.699.316.147.001
d. Total Production Cost (TPC)
: Rp 4.770.808.518.856
e. Sales
: Rp 5.730.802.178.256
f. Laba Bersih
: Rp 748.795.054.331
g. Pay Out Time (POT)
: 1 tahun 11 bulan
h. Break Event Point (BEP)
: 43,45 %
i. Rate of Return (ROR)
: 28,22 %
Berdasarkan data-data di atas dapat disimpulkan bahwa prarancangan pabrik biodiesel
dengan kapasitas produksi 300.000 ton/tahun layak dilanjutkan ke tahap rancangan.
Biodiesel plant design aims to design a biodiesel production facility based on crude palm oil (CPO), methanol, and NaOH as a catalyst. The production process used is transesterification, with the initial stage of FFA removal through adsorption using bentonite and washing using warm water for the purification. The plant is planned to operate for 330 days per year continuously for 24 hours per day, with a production capacity of 300.000 tons per year. The planned company form is a limited liability company (PT) using a line and staff organizational structure. In addition, the labor requirement in running the company is 124 people. The plant location is planned in Cot Lagam CM Village, Woyla District, West Aceh Regency, Aceh Province, Indonesia, with an area of 21.337 m 2 . The water source used comes from the Woyla River with a requirement of 100.755,69 kg/hour. Electricity needs will be supplied by the State Electricity Company (PLN) and a generator with a power capacity of 805,93 kW. The results of the economic analysis are as follows: a. Fixed Capital Investment (FCI) : Rp 1.444.418.724.951 b. Working Capital Investment (WCI) : Rp 254.897.422.050 c. Total Capital Investment (TCI) : Rp 1.699.316.147.001 d. Total Production Cost (TPC) : Rp 4.770.808.518.856 e. Sales : Rp 5.730.802.178.256 f. N e t P r o f i t : Rp 748.795.054.331 g. Pay Out Time (POT) : 1 Years 11 Months h. Break Event Point (BEP) : 43,45 % i. Rate of Return (ROR) : 28,22 % Based on data above, it can be concluded that the Premilinary Design of the biodiesel plant with a production capacity of 300.000 tons/year is feasible to proceed to the detaileddesign stage.
PRARANCANGAN PABRIK BIODIESEL DARI CRUDE PALM OIL (CPO) DENGAN KAPASITAS PRODUKSI 18.500 TON/TAHUN (Zahrul Umran, 2024)
PRARANCANGAN PABRIK BI0DIESEL DARI CRUDE PALM OIL (CPO) DENGAN KAPASITAS PRODUKSL 18.500 TON/TAHUN (Ivan Rezka Winata, 2024)
PRARANCANGAN PABRIK BIODIESEL DARI CRUDE PALM OIL (CPO) DENGAN KAPASITAS PRODUKSI 30.400 TON/TAHUN (Syafrizal, 2024)
PRARANCANGAN PABRIK BIODIESEL DARI MIKROALGA CHLORELLA SP DENGAN KAPASITAS PRODUKSI 80.000 TON/TAHUN (Erwinsyah Putra, 2025)
PRARANCANGAN PABRIK BIODIESEL DARI CRUDE PALM OIL (CPO) DENGAN KAPASITAS PRODUKSI I9.000 TON/TAHUN (Deswira Usman, 2025)