Electronic Theses and Dissertation
Universitas Syiah Kuala
SKRIPSI
PRARANCANGAN PABRIK GULA SEMUT DARI NIRA AREN (ARENGA PINNATA) DENGAN KAPASITAS 5600 TON/TAHUN
Pengarang
AYDANA TUSHIFA - Personal Name;
Dosen Pembimbing
Hesti Meilina - 197605052003122001 - Dosen Pembimbing I
Abubakar - 196108071990021001 - Dosen Pembimbing I
Darmadi - 196603231993031003 - Dosen Pembimbing I
T. Mukhriza - 198010032006041003 - Dosen Pembimbing I
Nomor Pokok Mahasiswa
2104103010063
Fakultas & Prodi
Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201
Kata Kunci
Penerbit
Banda Aceh : Fakultas Teknik., 2025
Bahasa
Indonesia
No Classification
660
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
ABSTRAK
Prarancangan pabrik gula semut ini menggunakan nira aren sebagai bahan baku. Kapasitas produksi pabrik gula semut ini adalah 5.600 ton/tahun dengan hari kerja 330 hari/tahun. Perseroan Terbatas (PT) adalah bentuk perusahaan yang direncanakan dengan menggunakan struktur garis dan staf. Kebutuhan tenaga kerja untuk menjalankan perusahaan ini berjumlah 148 orang. Lokasi pabrik direncanakan didirikan di Tapanuli Selatan, Provinsi Sumatera Utara dengan luas tanah sebesar 10.487 m2. Kebutuhan air untuk pabrik ini sebesar 8.940 kg/jam yang diperoleh dari PDAM Tirtanadi Tapanuli Selatan. Sumber listrik diperoleh dari generator dengan sumber daya 500 kW.
Hasil analisa ekonomi yang diperoleh adalah sebagai berikut:
1. Fixed Capital Investment (FCI) = Rp 128.886.835.809
2. Working Capital Investment (WCI) = Rp 22.744.735.731
3. Total Capital Investment (TCI) = Rp 151.631.571.540
4. Total Production Cost (TPC) = Rp 350.941.361.496
5. Sales Cost (SC) = Rp 421.975.763.045
6. Laba bersih = Rp 53.275.801.162
7. POT = 4,24 tahun
8. Break Event Point (BEP) = 38 %
9. Internal Rate of Return (IRR) = 28,36%
10. Rate of Return (ROR) = 47 %
ABSTRACT This Palm Sugar plant proposal uses palm sap as raw material. The production capacity of the Palm Sugar plant is 5,600 tons/year with 330 working days/year. Limited Liability Company (PT) is a form of company that is planned using a line and staff structure. Labor requirements to run this company 148 people. The factory location is planned to be established in South Tapanuli, North Sumatera Province with a land area of 10,487 m2. Nusantra Tenggara Timur with a land area of 20,490 m2. The water requirement for this factory is 8,940 kg/hour which is obtained from the South Tapanuli water supply system. The electricity source is obtained from a generator with a power source of 500 kW. From economic analisys was obtained: 1. Fixed Capital Investment (FCI) = Rp 188.886.835.809 2. Working Capital Investment (WCI) = Rp 22.744.735.731 3. Total Capital Investment (TCI) = Rp 151.631.571.540 4. Total Production Cost (TPC) = Rp 350.941.361.496 5. Sales Cost (SC) = Rp 421.975.763.045 6. Laba bersih = Rp 53.275.801.162 7. POT = 4,24 tahun 8. Break Event Point (BEP) = 38 % 9. Internal Rate of Return (IRR) = 28,36% 10. Rate of Return (ROR) = 47 %
PRARANCANGAN PABIK CRYSTAL PALM SUGAR DARI NIRA KELAPA DENGAN KAPASITAS PRODUKSI 50.000 TON/TAHUN (RAJA AZKIA UMAYROH, 2024)
PRARANCANGAN PABIK CRYSTAL PALM SUGAR DARI NIRA KELAPA DENGAN KAPASITAS PRODUKSI 50.000 TON/TAHUN (Tiara Lauzia, 2024)
PRARANCANGAN PABIK CRYSTAL BROWN SUGAR DARI BAHAN BAKU TEBU DENGAN KAPASITAS PRODUKSI RN400 TON/TAHUN (T. AL HARIS RAMADHAN, 2022)
PRARANCANGAN PABRIK CRYSTAL BROWN SUGAR MENGGUNAKAN BAHAN BAKU TEBU DENGAN KAPASITAS PRODUKSI 400 TON/TAHUN (MUHAMMAD ZAKIYAMMAN, 2022)
PRARANCANGAN PABRIK CRYSTAL PALM SUGAR MENGGUNAKAN BAHAN BAKU NIRA LONTAR DENGAN KAPASITAS PRODUKSI 2.300 TON/TAHUN (RYAN ADITYA, 2022)