PROYEK PEMBANGUNAN RUMAH SUSUN YAYASAN TEUNGKU CHIEK PANTE GEULIMA
Pengarang
MUHAMMAD WILDAN - Personal Name;
Dosen Pembimbing
Febriyanti Maulina - 197802242008122002 - Dosen Pembimbing I
Ibnu Abbas - 196203281989031002 - Dosen Pembimbing II
Nomor Pokok Mahasiswa
2204001010003
Fakultas & Prodi
Fakultas Teknik / Teknik Sipil (D3) / PDDIKTI : 22401
Penerbit
Banda Aceh : ., 2025
Bahasa
Indonesia
No Classification
690.831 4
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
Penelitian ini membahas metode pelaksanaan pekerjaan kolom, estimasi volume dan kebutuhan material, serta evaluasi penerapan keselamatan kerja pada proyek Pembangunan Rumah Susun Yayasan Teungku Pante Chiek Geulima. Tahapan pelaksanaan kolom yang diamati meliputi marking as kolom, penulangan, checklist oleh quality control, pemasangan dan pembongkaran bekisting, serta pengecoran. Hasil perhitungan menunjukkan bahwa volume beton ready mix pada kolom K1 sebesar 15,61 m³ dan pada kolom K5 sebesar 0,37 m³. Kebutuhan tulangan, bekisting, serta bahan pendukung lainnya dihitung secara rinci, menghasilkan total Rencana Anggaran Biaya (RAB) sebesar Rp126.921.977,91. Perhitungan kebutuhan material juga menunjukkan jumlah spesifik untuk masing-masing kolom, termasuk besi, paku, plywood, dan kayu dolken.
Selain aspek teknis, penelitian ini juga mengevaluasi penerapan keselamatan kerja (K3) di lokasi proyek. Berdasarkan observasi lapangan, ditemukan bahwa implementasi K3 belum maksimal. Beberapa kekurangan yang mencolok adalah penggunaan alat pelindung diri (APD) yang tidak konsisten, minimnya rambu keselamatan di area berbahaya, serta rendahnya kesadaran pekerja terhadap pentingnya keselamatan. Minimnya pelatihan keselamatan secara berkala turut menjadi faktor risiko terhadap potensi kecelakaan kerja. Oleh karena itu, penulis merekomendasikan validasi data yang akurat, penggunaan metode analisis yang lebih presisi, serta peningkatan manajemen keselamatan kerja melalui pelatihan dan pengawasan yang lebih intensif untuk menjamin kualitas proyek dan keselamatan peker
This study discusses the column construction method, volume estimation and material requirements, and an evaluation of occupational safety implementation in the Teungku Pante Chiek Geulima Foundation Flats Construction project. The observed column construction stages included column axis marking, reinforcement, quality control checklists, formwork installation and dismantling, and casting. Calculations indicate that the volume of ready-mix concrete for column K1 is 15.61 m³ and for column K5, 0.37 m³. The requirements for reinforcement, formwork, and other supporting materials were calculated in detail, resulting in a total Cost Budget Plan (RAB) of Rp126,921,977.91. The material requirements calculation also indicated specific quantities for each column, including iron, nails, plywood, and dolken wood. In addition to technical aspects, this study also evaluated the implementation of occupational safety (OHS) at the project site. Based on field observations, it was found that OHS implementation was suboptimal. Several glaring deficiencies included inconsistent use of personal protective equipment (PPE), a lack of safety signs in hazardous areas, and low worker awareness of the importance of safety. The lack of regular safety training is also a risk factor for potential workplace accidents. Therefore, the authors recommend accurate data validation, the use of more precise analytical methods, and improved occupational safety management through more intensive training and supervision to ensure project quality and worker safety.
PROYEK PEMBANGUNAN RUMAH SUSUN YAYASANRNTEUNGKU CHIEK PANTE GEULIMA (MUHAMMAD WILDAN, 2025)
PROYEK PEMBANGUNAN RUMAH SUSUN YAYASAN TEUNGKU CHIEK PANTE GEULIMA (MUHAMMAD WILDAN, 2025)
DARI DAYAH KE YAYASAN PENDIDIKAN TINGGI: PERKEMBANGAN LEMBAGA PENDIDIKAN TEUNGKU CHIK PANTE KULU BANDA ACEH, 1962-2017 (ANNISA RAHMI, 2018)
PROYEK PEMBANGUNAN RUMAH SUSUN ASN PUPR DUKUNGAN UNTUK PON (RISTI AYDHIRA, 2024)
RUMAH SUSUN SEDERHANA MILIK KAMPUNG PUSONG LHOKSEUMAWE (TEUKU ZULFAKRI, 2014)