PRARANCANGAN PABRIK NATRIUM KARBONAT DARI BATU KAPUR RNDAN NATRIUM KLORIDA DENGAN MENGGUNKAN PROSES SOLVAY RNBERKAPASITAS 200.000 TON/TAHUN | ELECTRONIC THESES AND DISSERTATION

Electronic Theses and Dissertation

Universitas Syiah Kuala

    SKRIPSI

PRARANCANGAN PABRIK NATRIUM KARBONAT DARI BATU KAPUR RNDAN NATRIUM KLORIDA DENGAN MENGGUNKAN PROSES SOLVAY RNBERKAPASITAS 200.000 TON/TAHUN


Pengarang

Muhamad Rasyid Rida - Personal Name;

Dosen Pembimbing

Sri Aprilia - 196704121993032001 - Dosen Pembimbing I
Zuhra - 197403181999032001 - Dosen Pembimbing II
Yunardi - 196009151988101001 - Penguji
Hesti Meilina - 197605052003122001 - Penguji



Nomor Pokok Mahasiswa

2004103010005

Fakultas & Prodi

Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201

Subject
-
Kata Kunci
-
Penerbit

Banda Aceh : Fakultas Teknik Kimia., 2024

Bahasa

No Classification

-

Literature Searching Service

Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)

ABSTRAK
Prarancangan pabrik Natrium Karbonat dari Batu Kapur dan Natrium Klorida
sebagai bahan baku. Kapasitas pabrik Natrium Karbonat ini adalah 200.000
Ton/Tahun dengan hari kerja 330 hari/tahun. Bentuk perusahaan yang direncanakan
adalah Perseroan Terbatas (PT) dengan menggunakan metode struktur garis dan
staf. Kebutuhan tenaga kerja untuk menjalankan perusahaan ini berjumlah 160
orang. Lokasi pabrik direncanakan didirikan di Indarung, Padang, Sumatera Barat
dengan luas tanah 60.000 m2. Sumber air pabrik Natrium Karbonat ini berasal dari
Sungai Lubuk Paraku, Indarung, Padang, Sumatera Barat dan untuk memenuhi
kebutuhan listrik diperoleh dari perusahaan dengan daya pada Generator sebesar
6.388,39 kW.
Hasil analisa ekonomi yang diperoleh adalah:
a. Fixed Capital Investment (FCI) = Rp. 2.845.906.337.562
b. Working Capital Investment (WCI) = Rp. 711.476.584.390
c. Total Capital Investment (TCI) = Rp. 3.557.382.921.953
d. Total Biaya Produksi = Rp. 6.146.807.185.020
e. Hasil Penjualan = Rp. 7.900.088.076.244
f. Laba bersih = Rp. 1.314.960.668.417
g. Pay Out Time (POT) = 3,94 tahun
h. Break Event Point (BEP) = 29,35%
i. Internal Rate of Return (IRR) = 34,29%
Berdasarkan studi kelayakan teknis dan ekonomis diatas, maka dapat disimpulkan
bahwa prarancangan pabrik natrium karbonat ini layak untuk dilanjutkan ke tahap
rancangan.

ABSTRACT Pre-design of a Sodium Carbonate factory from Limestone and Sodium Chloride as raw materials. The capacity of this Sodium Carbonate factory is 200,000 tons/year with working days of 330 days/year. The planned company form is a Limited Liability Company (PT) using the line and staff structure method. The workforce required to run this company is 160 people. The factory location is planned to be established in Indarung, Padang, West Sumatra with a land area of 60,000 m2. The water source for the sodium carbonate factory comes from the Lubuk Paraku River, Indarung, Padang, West Sumatra and the electricity needs obtained from the company with a generator power of 6,388.39 kW. The results of the economic analysis are: a. Fixed Capital Investment (FCI) = Rp. 2.845.906.337.562 b. Working Capital Investment (WCI) = Rp. 711.476.584.390 c. Total Capital Investment (TCI) = Rp. 3.557.382.921.953 d. Total Biaya Produksi = Rp. 6.146.807.185.020 e. Hasil Penjualan = Rp. 7.900.088.076.244 f. Laba bersih = Rp. 1.314.960.668.417 g. Pay Out Time (POT) = 3,94 tahun h. Break Event Point (BEP) = 29,35% i. Internal Rate of Return (IRR) = 34,29% Based on the technical and economic feasibility studies above, it can be concluded that the preliminary plant design of the sodium carbonate plant is feasible to proceed to the design stage.