PRARANCANGAN PABRIK PULP DARI PELEPAH KELAPA SAWIT DENGAN PROSES ACETOSOLV DENGAN KAPASITAS PRODUKSI 250.000 TON/TAHUN | ELECTRONIC THESES AND DISSERTATION

Electronic Theses and Dissertation

Universitas Syiah Kuala

    SKRIPSI

PRARANCANGAN PABRIK PULP DARI PELEPAH KELAPA SAWIT DENGAN PROSES ACETOSOLV DENGAN KAPASITAS PRODUKSI 250.000 TON/TAHUN


Pengarang

Thiara Puspa Rahmania - Personal Name;

Dosen Pembimbing

Cut Meurah Rosnelly - 196801091994032003 - Dosen Pembimbing I
Umi Fathanah - 197404032000122001 - Dosen Pembimbing II



Nomor Pokok Mahasiswa

2004103010046

Fakultas & Prodi

Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201

Subject
-
Kata Kunci
-
Penerbit

Banda Aceh : Fakultas Teknik Kimia., 2024

Bahasa

No Classification

-

Literature Searching Service

Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)

Prarancangan pabrik pulp menggunakan pelepah kelapa sawit dan asam asetat
sebagai bahan baku. Pabrik ini dirancang untuk memproduksi pulp melalui proses
acetosolv dengan penggunaan asam asetat sebagai pelarut organik. Kapasitas
produksi pabrik ini adalah 250.000 ton/tahun dengan waktu operasi 330 hari/tahun
dan 24 jam/hari. Bentuk perusahaan yang direncanakan adalah Perseroan Terbatas
(PT) dengan menggunakan metode struktur organisasi garis dan staf. Kebutuhan
tenaga kerja untuk menjalankan perusahaan ini berjumlah 133 orang. Pabrik ini
direncanakan didirikan di Kawasan Industri Bengkalis, Kabupaten Bengkalis, Riau
dengan luas tanah 16.304 m2
. Sumber air pabrik ini berasal dari Sungai Siak,
sedangkan listrik diperoleh dari generator diesel dengan daya 27.916.792 kW.
Hasil analisa ekonomi yang diperoleh adalah sebagai berikut :
a. Fixed Capital Invesment = Rp 1.271.960.636.793,-
b. Working Capital Invesment = Rp 141.328.959.644,-
c. Total Capital Invesment = Rp 1.413.289.596.436,-
d. Total Production Cost = Rp 6.009.045.611.749,-
e. Sales Cost = Rp 6.759.550.885.212,-
f. Laba bersih = Rp 562.878.955.097,-
g. Pay Out Time (POT) = 3,6 tahun
h. Break Event Point (BEP) = 35%
i. Internal Rate of Return (IRR) = 28,77%.
j. Rate of Return (ROR) = 40 %
Berdasarkan studi kelayakan teknis dan ekonomis diatas, maka dapat disimpulkan
bahwa prarancangan pabrik pulp ini layak untuk dilanjutkan ke tahap rancangan.

The pulp mill design uses palm fronds and acetic acid as raw materials. This factory is designed to produce pulp through the acetosolv process using acetic acid as an organic solvent. The production capacity of this factory is 250,000 tons/year with an operating time of 330 days/year and 24 hours/day. The planned company form is a Limited Liability Company (PT) using the line and staff organizational structure method. The workforce required to run this company is 133 people. This factory is planned to be established in the Bengkalis Industrial Area, Bengkalis Regency, Riau with a land area of 16,304 m2. The water source for this factory comes from the Siak River, while electricity is obtained from a diesel generator with a power of 27,916,792 kW. The results of the economic analysis obtained are as follows: a. Fixed Capital Invesment = Rp 1.271.960.636.793,- b. Working Capital Invesment = Rp 141.328.959.644,- c. Total Capital Invesment = Rp 1.413.289.596.436,- d. Total Production Cost = Rp 6.009.045.611.749,- e. Sales Cost = Rp 6.759.550.885.212,- f. Net Profit = Rp 562.878.955.097,- g. Pay Out Time (POT) = 3,6 years h. Break Event Point (BEP) = 35% i. Internal Rate of Return (IRR) = 28,77%. j. Rate of Return (ROR) = 40 % Based on the technical and economic feasibility studies above, it can be concluded that the preliminary design of the pulp plant is feasible to proceed to the design stage