PRARANCANGAN PABRIK PUPUK TRIPLE SUPERPHOSPHATE DENGAN KAPASITAS PRODUKSI 370.000 TON/TAHUN
Pengarang
NYAK MIRANDA ANGKASAH - Personal Name;
Dosen Pembimbing
Lia Mairiza - 197405232000032001 - Dosen Pembimbing I
Mirna Rahmah Lubis - 197710012003122001 - Dosen Pembimbing II
Nomor Pokok Mahasiswa
1804103010029
Fakultas & Prodi
Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201
Subject
Kata Kunci
Penerbit
Banda Aceh : Fakultas Teknik., 2023
Bahasa
No Classification
-
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
Prarancangan pabrik triple superphosphate (TSP) ini menggunakan bahan
batuan fosfat dan asam fosfat. Kapasitas produksi adalah sebesar 370.000
ton/tahun dengan waktu operasi 330 hari/tahun dan 24 jam/hari. Bentuk
perusahaan yang direncanakan adalah Perseroan Terbatas (PT) dengan
menggunakan metode struktur organisasi garis dan staf. Kebutuhan tenaga kerja
untuk menjalankan perusahaan ini berjumlah 179 orang. Lokasi pabrik
direncanakan didirikan di daerah Kecamatan Juwana, Kabupaten Pati, Jawa
Tengah. Sumber air untuk kebutuhan pabrik ini berasal dari kali Juwana dan untuk
memenuhi kebutuhan listrik sebesar 0,648 MW disuplai dari unit utilitas. Hasil
analisa ekonomi Prarancangan Pabrik TSP dengan kapasitas 370.000 Ton/tahun
diperoleh sebagai berikut :
1.Fixed Capital Investment (FCI) Rp 119.507.668.231
2.Working Capital Investment (WCI) Rp 22.407.687.793
3.Total Capital Investment (TCI) Rp 149.384.585.289
4.Total biaya produksi (TPC) Rp 130.051.351.752
5.Hasil penjualan (SC) Rp 219.472.313.507
6.Laba bersih Rp 67.065.721.316
7.Pay Of Time (POT) 2,8 tahun
8.Break Event Point (BEP) 31%
9.Internal Rate of Return (IRR) 32,64%
10.Rate of Return (ROR) 45%
The predesign of this triple superphosphate (TSP) plant uses phosphate rock and phosphoric acid. Production capacity is 370,000 tons / year with an operating time of 330 days / year and 24 hours / day. The planned company form is a Limited Liability Company (PT) using the organizational structure method of lines and staff. The need for manpower to run this company amounts to 179 people. The factory location is planned to be established in Juwana District, Pati Regency, Central Java. The water source for the needs of this plant comes from the Juwana river and to meet the electricity needs of 0.648 MW is supplied from utility units. The results of the economic analysis of the TSP Plant Predesign with a capacity of 370,000 tons / year were obtained as follows: 1.Fixed Capital Investment (FCI) IDR 119.507.668.231 2.Working Capital Investment (WCI) IDR 22.407.687.793 3.Total Capital Investment (TCI) IDR 149.384.585.289 4.Total production cost (TPC) IDR 130,051,351,752 5.Sales result (SC) IDR 219,472,313,507 6.Net profit IDR 67,065,721,316 7.Pay Of Time (POT) 2.8 years 8.Break Event Point (BEP) 31% 9.Internal Rate of Return (IRR) 32,64% 10.Rate of Return (ROR) 45%
PRARANCANGAN PABRIK PUPUK TRIPLE SUPERPHOSPHATE DENGAN KAPASITAS PRODUKSI 370.000 TON/TAHUN (NYAK MIRANDA ANGKASAH, 2023)
PRARANCANGAN PABRIK PUPUK TRIPLE SUPERPHOSPHATE MENGGUNAKAN PROSES KUHLMANN DENGAN KAPASITAS PRODUKSI 400.000 TON/TAHUN (Fia Utami Prananda Putri, 2021)
PRARANCANGAN PABRIK PUPUK TRIPLE SUPERPHOSHATE DENGAN PROSES BRIDGER MENGGUNAKAN KAPASITAS PRODUKSI 80.000 TON/TAHUN (HUSNAN ZUHRY, 2017)
PRARANCANGAN PABRIK PUPUK TRIPLE SUPERPHOSHATE DENGAN PROSES BRIDGER MENGGUNAKAN KAPASITAS PRODUKSI 80.000 TON/TAHUN (M. ILHAM WAHYUDI, 2017)
PRARANCANGAN PABRIK PUPUK TRIPEL SUPERFOSFAT (TSP) DENGAN KAPASITAS PRODUKSI 250.000 TON/TAHUN (Fakhrial, 2024)