SKRIPSI
PRARANCANGAN PABRIK SIKLOHEKSANA DARI BENZENA DAN HIDROGEN DENGAN MENGGUNAKAN PROSES HIDROGENASI KAPASITAS 120.000 TON/TAHUN
Pengarang
Retika Septi Diana Utari - Personal Name;
Dosen Pembimbing
Izarul Machdar - 196509201992031003 - Dosen Pembimbing I
Wahyu Rinaldi - 198101062006041001 - Dosen Pembimbing II
Nomor Pokok Mahasiswa
1904103010028
Fakultas & Prodi
Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201
Subject
Penerbit
Banda Aceh : Fakultas Teknik., 2023
Bahasa
Indonesia
No Classification
546.2
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
Prarancangan pabrik sikloheksana (C6H12) menggunakan benzena (C6H6) dan hidrogen (H2) sebagai bahan baku. Pabrik ini dirancang untuk memproduksi sikloheksana melalui proses hidrogenasi benzena dengan penggunaan nikel sebagai katalis. Kapasitas produksi pabrik ini adalah 120.000 ton/tahun dengan waktu operasi 330 hari/tahun dan 24 jam/hari. Bentuk perusahaan yang direncanakan adalah Perseroan Terbatas (PT) dengan menggunakan metode struktur organisasi garis dan staf. Kebutuhan tenaga kerja untuk menjalankan perusahaan ini berjumlah 99 orang. Pabrik ini direncanakan didirikan di Kawasan Industri Krakatau Steel, Cilegon, Banten, Jawa Barat dengan luas tanah 121.061m2. Sumber air pabrik ini berasal dari PT. Krakatau Tirta Industri (KTI), sedangkan listrik diperoleh dari Perusahaan Listrik Negara (PLN) dan generator diesel dengan daya 1 MW.
Hasil analisa ekonomi yang diperoleh adalah sebagai berikut :
a. Fixed Capital Investment (FCI) = Rp 592.747.070.670
b. Working Capital Investment (WCI) = Rp 104.602.424.236
c. Total Capital Investment (TCI) = Rp 697.349.494.906
d. Total Production Cost (TPC) = Rp 2.897.381.068.231
e. Selling Cost (SC) = Rp 3.505.756.090.994
f. PBP = 2,2 tahun
g. Break Event Point (BEP) = 35,82%
h. Internal Rate of Return (IRR) = 52,39%
i. Return on Investment (ROI) = 32,71%
Berdasarkan studi kelayakan teknis dan ekonomis diatas, maka dapat disimpulkan bahwa prarancangan pabrik sikloheksana ini layak untuk dilanjutkan ke tahap rancangan.
This preliminary of sikloheksana (C6H6) plant design uses benzena (C6H6) and hidrogen (H2) as raw materials. This chemical plant is designed to cyclohexane using benzene hydrogenation process and nikel as the catalyst. The production capacity of this chemical plant is 120,000 tons/year with 330 working days/year and 24 hours/day. The planned form of the company is a Limited Liability Company (PT) using the line and staff organizational structure method with 99 total employees. The location of the plant is planned to be established in Krakatau Steel, Cilegon, Banten, Jawa Barat with a land area of 121.061 m2. The water sources come from PT. Krakatau Tirta Industri (KTI), while the electricity is obtained from the State Electricity Company (PLN) and a diesel generator with 1 MW total power. The results of the economic analysis obtained are as follows: a. Fixed Capital Investment (FCI) = Rp 592.747.070.670 b. Working Capital Investment (WCI) = Rp 104.602.424.236 c. Total Capital Investment (TCI) = Rp 697.349.494.906 d. Total Production Cost (TPC) = Rp 2.897.381.068.231 e. Selling Cost (SC) = Rp 3.505.756.090.994 f. PBP = 2,2 years g. Break Event Point (BEP) = 35,82% h. Internal Rate of Return (IRR) = 52,39% i. Return on Investment (ROI) = 32,71% Based on the technical and economic feasibility studies above, it can be concluded that the preliminary design of the cyclohexane plant is feasible to proceed to the design stage.
PRARANCANGAN PABRIK SIKLOHEKSANA DARI BENZENA DAN HIDROGEN DENGAN MENGGUNAKAN PROSES HIDROGENASI KAPASITAS 120.000 TON/TAHUN (Retika Septi Diana Utari, 2023)
PRARANCANGAN PABRIK HIDROGEN DARI BATUBARA DENGAN KAPASITAS PRODUKSI 9.000 TON/TAHUN (AULIA MOEDA MAKARIM, 2017)
PRARANCANGAN PABRIK HIDROGEN DARI BATUBARA DENGAN KAPASITAS PRODUKSI 9.000 TON/TAHUN (Rahmat Hidayat, 2017)
PRARANCANGAN PABRIK HIDROGEN CAIR DARI TANDAN KOSONG SAWIT DENGAN KAPASITAS BAHAN BAKU 60.000 TON/TAHUN (Naluri Iqbal Shiddiq/Putra Utama, 2024)
PRARANCANGAN PABRIK HIDROGEN DARI GAS ALAM MENGGUNAKAN PROSES STEAM REFORMING DENGAN KAPASITAS 15.000 TON/TAHUN (Muhammad Nazir, 2024)