PRARANCANGAN PABRIK METIL TERT BUTIL ETER DARI METANOL DAN ISOBUTENE DENGAN KAPASITAS PRODUKSI 560.000 TON/TAHUN
Pengarang
HAJID ZAFRAN - Personal Name;
Dosen Pembimbing
Nomor Pokok Mahasiswa
1804103010055
Fakultas & Prodi
Fakultas Teknik / Teknik Kimia (S1) / PDDIKTI : 24201
Subject
Kata Kunci
Penerbit
Banda Aceh : Fakultas Teknik., 2023
Bahasa
No Classification
-
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
Prarancangan pabrik Methyl tertiary-butyl ether dari metanol dan isobutene sebagai bahan baku. Pabrik ini dirancang untuk memproduksi Methyl tertiarybutyl ether melalui proses ARCO dengan penggunaan Amberlyst-15 sebagai katalis. Kapasitas produksi pabrik ini adalah 560.000 ton/tahun dengan waktu operasi 330 hari/tahun dan 24 jam/hari. Bentuk perusahaan yang direncanakan adalah Perseroan Terbatas (PT) dengan menggunakan metode struktur organisasi garis dan staf. Kebutuhan tenaga kerja untuk menjalankan perusahaan ini berjumlah 156 orang. Pabrik ini direncanakan didirikan di Kota Bontang, Provinsi KalimantanTimur dengan luas tanah 23.346 m2 . Sumber air pabrik ini berasal dari Laut, sedangkan listrik diperoleh dari Perusahaan Listrik Negara (PLN) dan
generator diesel dengan daya 3.679,093 MW.
Hasil analisa ekonomi yang diperoleh adalah sebagai berikut :
a. Fixed Capital Investment (FCI) = Rp. 1.026.319.756.362,15,-
b. Working Capital Investment (WCI) = Rp. 839.716.164.296,30,-
c. Total Capital Investment (TCI) = Rp. 1.866.035.920.658,45,-
d. Total Production Cost (TPC) = Rp 13.462.165.762.050,70,-
e. Total Revenue (TR) = Rp. 14.175.770.159.540,70,-
f. Laba Bersih = Rp. 535.203.298.117,46,-
g. POT = 5,07 tahun
h. Break Event Point (BEP) = 40,77 %
i. Internal Rate of Return (IRR) = 25,42 %
j. Rate Of Return (ROR) = 29 %
Berdasarkan studi kelayakan teknis dan ekonomis diatas, maka dapat disimpulkan bahwa Prarancangan Pabrik MTBE ini layak untuk dilanjutkan ke tahap rancangan.
This preliminary Methyl tertiary-butyl ether plant design uses Isobutylene and Methanol as raw materials. This chemical plant is designed to Methyl tertiary butyl ether using the ARCO process and Amberlyst-15 as the catalyst. The production capacity of this chemical plant is 560,000 tons/year with 330 working days/year and 24 hours/day. The planned form of the company is a Limited Liability Company (PT) using the line and staff organizational structure method with 154 total employees. The location of the plant is planned to be established in Bontang City, East Kalimantan, with a land area of 23.346 m2. The water sources come from the Cidanau river, while the electricity is obtained from the State Electricity Company (PLN) and a diesel generator with 3.679,093 MW of total power. The results of the economic analysis obtained are as follows: a. Fixed Capital Investment (FCI) = Rp. 1.026.319.756.362,15,- b. Working Capital Investment (WCI) = Rp. 839.716.164.296,30,- c. Total Capital Investment (TCI) = Rp. 1.866.035.920.658,45,- d. Total Production Cost (TPC) = Rp 13.462.165.762.050,70,- e. Total Revenue (TR) = Rp. 14.175.770.159.540,70,- f. Laba Bersih = Rp. 535.203.298.117,46,- g. POT = 5,07 years. h. Break Event Point (BEP) = 40,77 % i. Internal Rate of Return (IRR) = 25,42 % j. Rate Of Return (ROR) = 29 % Based on the technical and economic feasibility studies above, it can be concluded that the preliminary design of the MTBE Plant is feasible to proceed to the design stage.
PRARANCANGAN PABRIK DIMETIL ETER BERBAHAN BAKU METANOL DENGAN KAPASITAS PRODUKSI 100.000 TON/TAHUN (RAHMAT ALFANO, 2021)
PRARANCANGAN PABRIK DIMETIL ETER BERBAHAN BAKU METANOL DENGAN KAPASITAS PRODUKSI 100.000 TON/TAHUN (ASWIN SISWANTO, 2021)
PRARANCANGAN PABRIK N-BUTIL ASETAT DARI ASAM ASETAT DAN BUTANOL MENGGUNAKAN REAKSI ESTERIFIKASI DENGAN KAPASITAS 40.000 TON/TAHUN (Amara Nahdyatul Hikmah Dasmara, 2023)
PRARANCANGAN PABRIK N-BUTIL ASETAT DARI ASAM ASETAT DAN BUTANOL MENGGUNAKAN REAKSI ESTERIFIKASI DENGAN KAPASITAS 40.000 TON/TAHUN (Fazira, 2023)
PRARANCANGAN PABRIK METIL KLORIDA MENGGUNAKAN PROSES HIDROKLORINASI METANOL DENGAN KAPASITAS PRODUKSI 50.000 TON/TAHUN (Al Hayyu Lathifu, 2023)