PRIORITAS PENANGANAN REHABILITASI RENOVASI DANRNPENILAIAN KONDISI SARANA PRASARANARNSEKOLAH DAN MADRASAH DI KABUPATEN ACEH BESAR
Pengarang
Zulfadhli - Personal Name;
Dosen Pembimbing
Muttaqin - 196606151990091001 - Dosen Pembimbing I
Taufiq S. - 196309221990021001 - Dosen Pembimbing II
Abdullah - 196403211989031002 - Penguji
Munira Sungkar - 197606062000122001 - Penguji
Nomor Pokok Mahasiswa
1804201010035
Fakultas & Prodi
Fakultas Teknik / Teknik Sipil (S2) / PDDIKTI : 22101
Subject
Kata Kunci
Penerbit
Banda Aceh : Program Studi Magister Teknik Sipil., 2022
Bahasa
No Classification
-
Literature Searching Service
Hard copy atau foto copy dari buku ini dapat diberikan dengan syarat ketentuan berlaku, jika berminat, silahkan hubungi via telegram (Chat Services LSS)
PRIORITAS PENANGANAN REHABILITASI RENOVASI DAN
PENILAIAN KONDISI SARANA PRASARANA
SEKOLAH DAN MADRASAH DI KABUPATEN ACEH BESAR
Zulfadhli
NIM. 1804201010035
Program Studi Magister Teknik Sipil
Jurusan Teknik Sipil – Fakultas Teknik
Universitas Syiah Kuala
Abstrak
Berdasarkan Peraturan Presiden Nomor 43 Tahun 2019 Kementerian Pekerjaan Umum dan
Perumahan Rakyat melalui Balai Prasarana Permukiman Wilayah Aceh terus melaksanakan
percepatan rehabilitasi sarana prasarana sekolah/madrasah. Kabupaten Aceh Besar memiliki
sarana prasarana pendidikan berjumlah 376 sekolah/madrasah negeri, termasuk dalam
wilayah terluar
(perbatasan). Penelitain ini bertujuan untuk melakukan identifikasi dan
menganalisis penilaian tentang kondisi sarana prasarana sekolah/madrasah, serta
menganalisis prioritas penanganan rehabilitasi dan renovasi sekolah/madrasah di Kabupaten
Aceh Besar. Penelitian ini menggunakan metode mixed methods dimana kuesioner dijadikan
penentuan populasi dan instrumen melalui observasi dan survei. Sampel diperoleh sebanyak
79 sekolah/madrasah negeri di Kabupaten Aceh Besar. Teknik pengolahan data dilakukan
pada 31 sekolah/madrasah negeri yang teridentifikasi rusak berat/sedang, analisis penilaian
tingkat kerusakan sekolah/madrasah berdasarkan Surat Edaran Direktorat Jenderal Cipta
Karya Nomor 47 Tahun 2020. Teknik sampel yang digunakan adalah Purposive Sampling
dengan pertimbangan yang didasarkan pada pihak stakeholders. Responden ditetapkan
sebanyak 6 stakeholders bidang sarana prasarana. Kriteria yang ditinjau adalah
sekolah/madrasah negeri, memiliki minimal 1 ruang kelas rusak berat/sedang, berada di
wilayah 3T atau desa berkembang
(tertinggal, terdepan, dan terluar
), berada di lokasi/lahan
milik negara
(tercatat dalam aset negara
), tidak sedang mendapatkan bantuan pendanaan,
bangunan non permanent, dan jumlah siswa/i. Teknik analisis data digunakan Analisis Multi
Kriteria. Hasil penelitian menunjukkan bahwa kriteria yang dominan perlu dipertimbangkan
dalam penanganan rehabilitasi dan renovasi sarana prasarana sekolah/madrasah di
Kabupaten Aceh Besar adalah kriteria sekolah/madrasah negeri. Prioritas penanganan adalah
SMP N 2 Lembah Seulawah sebagai prioritas 1, SD N Bak Sukon sebagai prioritas 2, SMP
N 1 lembah Seulawah sebagai prioritas 3, SMP N 3 Kuta Cot Glie sebagai prioritas 4, SD N
Lamcot sebagai prioritas 5.
Kata Kunci: Sarana, Prasarana, Sekolah, Madrasah, Renovasi, Rehabilitasi.
PRIORITY HANDLING OF REHABILITATION RENOVATION AND ASSESSMENT OF THE CONDITION OF INFRASTRUCTURE SCHOOLS AND MADRASAHS IN ACEH BESAR DISTRICT Zulfadhli Student Number 1804201010035 Master Program of Civil Engineering Civil Engineering Department of Engineering Faculty University of Syiah Kuala Abstract Based on Presidential Regulation Number 43 of 2019, the Ministry of Public Works and Public Housing through the Aceh Regional Settlement Infrastructure Center continues to accelerate the rehabilitation of schools/madrasahs' infrastructure. Aceh Besar Regency has an educational infrastructure totaling 376 public schools/madrasahs, including in the outermost (border ) area. This research aims to identify and analyze the assessment of the condition of schools/madrasahs' infrastructure, as well as analyze the priorities for handling the rehabilitation and renovation of schools/madrasahs in Aceh Besar Regency. This study used a mixed-methods method where questionnaires were used as population and instrument determinations through observation and surveys. Samples were obtained from 79 public schools/madrasahs in Aceh Besar Regency. The processing techniques were carried out on 31 public schools/madrasahs identified as severely/moderately damaged, an analysis of the level of damage to schools/madrasahs based on the Circular Letter of the Directorate General of Cipta Karya Number 47 of 2020. The sampling technique used is Purposive Sampling with considerations based on stakeholders. Respondents were determined as many as 6 stakeholders in the field of infrastructure. The criteria reviewed are state schools/madrasahs, have at least 1 classroom heavily/moderately damaged, are in a 3T area or developing village (lagging, frontier, and outermost ), are in state-owned locations/lands (recorded in state assets ), are not currently receiving funding assistance, non-permanent buildings, and the number of students/i. The data analysis technique is used Multi-Criteria Analysis. The results showed that the dominant criterion that needs to be considered in handling the rehabilitation and renovation of schools/madrasahs infrastructure in Aceh Besar Regency is the criteria for state schools/madrasahs. The priority for handling is SMP N 2 Lembah Seulawah as priority 1, SD N Bak Sukon as priority 2, SMP N 1 lembah Seulawah as priority 3, SMP N 3 Kuta Cot Glie as priority 4, SD N Lamcot as priority 5. Keywords: Facilities, Infrastructure, Schools, Madrasahs, Renovation, Rehabilitation.
PENENTUAN PRIORITAS PENANGANAN JALAN DI KECAMATAN SEULIMEUM KABUPATEN ACEH BESAR (Fakhurriza, 2021)
PENILAIAN TINGKAT KERUSAKAN DAERAH PANTAI DAN PRIORITAS PENANGANANNYA RN(STUDI KASUS PADA SATUAN WILAYAH PENGAMANAN PANTAI (SWPP) BANDA ACEH (LISADIANTI, 2015)
STRATEGI KEPALA MADRASAH DALAM MENINGKATKAN MUTU PENDIDIKAN PADA MIN BUENGCALA KECAMATANRNKUTA BARO KABUPATEN ACEH BESAR (MUHAMMAD HADI, 2015)
PENENTUAN SKALA PRIORITAS PENANGANAN JALAN KABUPATEN PIDIE MENGGUNAKAN METODE ANALISIS MULTI KRITERIA (AMK) (THANTAWI, 2019)
EVALUASI TINGKAT KERUSAKAN PERMUKAAN JALAN DAN MENENTUKAN PRIORITAS PEMELIHARAAN JALAN (STUDI KASUS JALAN PROVINSI DI KABUPATEN ACEH BESAR) (RISDIAWATI, 2021)